Steel Authority of India Ltd. (SAIL) first blast furnace ‘Parvati’ situated at SAIL’s Rourkela Steel Plant (RSP) has been rebuilt under company’s modernization and expansion program and is successfully blown in today. SAIL-RSP’s Blast Furnace No.1 – Parvati is rebuilt with state-of-the-art features and additional capacity. The useful volume of this rebuilt furnace, in its new avatar, has increased from 1139 cubic meter to 1710 cubic metre, as a result of which theannual production capacity of the furnace will go up from 0.438 MT per annum to 1.015 MT per annum. The rebuilt blast furnace was blown-in by Mr.Ashwini Kumar, CEO, RSP.